Ashok and Anil undertake to do a piece of work for ₹4,500. Ashok alone could do the work in the 8 days and Anil in 12 days. With the assistance of Amar, they finished the work in 4 days. What is the share of Amar?
1
₹1,500
2
₹750
3
₹2,250
4
₹2,500
2
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A man, a woman and a boy can complete a job in 3, 5 and 15 days, respectively. How many boys must assist 1 man and 1 woman to complete the job in $\frac{1}{5}$ of a day?
1
67
2
35
3
56
4
47
3
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
If A, B and C can do a work in 6 days, 9 days and 11 days, respectively, then, working together, how many days will they take to do the work?
1
$1 \frac{52}{73}$
2
$4 \frac{52}{73}$
3
$2 \frac{52}{73}$
4
$3 \frac{52}{73}$
4
SSC CGL Tier I - 26th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
10 women take 16 days to complete a work which can be completed by 6 men in 8 days. 12 men started working and after 2 days 6 men left, and 5 women joined them. In how many days will the work be completed?
1
$3 \over 2$
2
$16 \over 5$
3
$5 \over 2$
4
$26 \over 5$