1
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ashok and Anil undertake to do a piece of work for ₹4,500. Ashok alone could do the work in the 8 days and Anil in 12 days. With the assistance of Amar, they finished the work in 4 days. What is the share of Amar?
1
₹1,500
2
₹750
3
₹2,250
4
₹2,500
2
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A man, a woman and a boy can complete a job in 3, 5 and 15 days, respectively. How many boys must assist 1 man and 1 woman to complete the job in $\frac{1}{5}$ of a day?
1
67
2
35
3
56
4
47
3
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
If A, B and C can do a work in 6 days, 9 days and 11 days, respectively, then, working together, how many days will they take to do the work?
1
$1 \frac{52}{73}$
2
$4 \frac{52}{73}$
3
$2 \frac{52}{73}$
4
$3 \frac{52}{73}$
4
SSC CGL Tier I - 26th July 2023 Shift 4
MCQ (Single Correct Answer)
+2
-0.5
Change Language
15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:
1
$5 \frac{5}{11}$
2
$4 \frac{3}{11}$
3
$7 \frac{2}{11}$
4
$6 \frac{4}{11}$
EXAM MAP