SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ram and Ramesh can do a work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh and Somesh work together, in how many days will they complete the work?
1
10
2
8
3
12
4
6
2
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work if he is assisted by both B and C on every third day?
1
10
2
15
3
12
4
18
3
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Benny can do a piece of work in 24 days. Chethan and David can do the same work individually in 36 and 48 days, respectively. All of them begin the work together. However, Benny leaves the work 4 days before the completion of work and Chethan leaves the work 10 days before the completion of the work. David worked till the end and completed the work. Find the number of days in which the work was completed.
1
16
2
20
3
18
4
15
4
SSC CGL Tier I - 27th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ashok and Anil undertake to do a piece of work for ₹4,500. Ashok alone could do the work in the 8 days and Anil in 12 days. With the assistance of Amar, they finished the work in 4 days. What is the share of Amar?
1
₹1,500
2
₹750
3
₹2,250
4
₹2,500
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12