1
SSC CGL Tier I - 27th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A can finish a job in 8 hours and B can finish the same job in 12 hours independently. If they work simultaneously, in how many hours can they do the same job?
1
4.8
2
3.7
3
4.5
4
3.2
2
SSC CGL Tier I - 27th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?
1
10 days
2
8 days
3
12 days
4
7 days
3
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
P, Q and R can complete a piece of work in 9, 12 and 18 days, respectively. Working together, how much work can they complete in one day?
1
$\frac{2}{3}$
2
$\frac{1}{2}$
3
$\frac{1}{3}$
4
$\frac{1}{4}$
4
SSC CGL Tier I - 27th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ram and Ramesh can do a work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh and Somesh work together, in how many days will they complete the work?
1
10
2
8
3
12
4
6
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12