The completion of a construction job may be delayed due to strike. The probability of strike is 0.6. The probability that the construction job gets completed on time if there is no strike is 0.85 and the probability that the construction job gets completed on time if there is a strike is 0.35. What is the probability that the construction job will not be completed on time ?
A
0.35
B
0.45
C
0.55
D
0.65
2
NDA Mathematics 4 September 2022
MCQ (Single Correct Answer)
+2.5
-0.83
Change Language

The mean and standard deviation (SD) of marks obtained by 50 students of a class in 4 subjects are given below :

Subject Mathematics Physics Chemistry Biology
Mean Marks 40 28 38 36
SD 15 12 14 16

Which one of the following subjects shows highest variability of marks ?

A
Mathematics
B
Physics
C
Chemistry
D
Biology
3
NDA Mathematics 4 September 2022
MCQ (Single Correct Answer)
+2.5
-0.83
Change Language

The mean and standard deviation (SD) of marks obtained by 50 students of a class in 4 subjects are given below :

Subject Mathematics Physics Chemistry Biology
Mean Marks 40 28 38 36
SD 15 12 14 16

What is the coefficient of variation of marks in Mathematics ?

A
37.5%
B
38.0%
C
38.5%
D
39.0%
4
NDA Mathematics 4 September 2022
MCQ (Single Correct Answer)
+2.5
-0.83
Change Language

Consider the following grouped frequency distribution :

Class 0-10 10-20 20-30 30-40 40-50 50-60
Frequency 1 2 4 6 4 3

What is the median of the distribution ?

A
34
B
34.5
C
35
D
35.5
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12