1
GATE CE 2017 Set 1
Numerical
+2
-0
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be________
Your input ____
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure.
The durations (expressed in days) of the activities are mentioned below the arrows.
The critical duration for this construction project is
Questions Asked from Critical Path Method (Marks 2)
Number in Brackets after Paper Indicates No. of Questions