1
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 3 English Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
A
25 and 1
B
1 and 1
C
0 and 0
D
81 and 0
GATE CE Subjects
Fluid Mechanics and Hydraulic Machines
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12