1
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A construction project consists of twelve activities. The estimated duration (in days) required
to complete each of the activities along with the corresponding network diagram is shown
below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,